In January, the percentage of central government projects facing delays reached its lowest point in 15 months, dropping to 42.8% from 46.6% the previous month, according to a report. Out of 1,821 registered projects, 617 were on time, 780 were delayed, 431 experienced cost overruns, and 255 had both time and cost overruns. The average time overrun for the 780 delayed projects was 36.13 months. Read The Rest at :
Disclaimer : Mymoneytimes implements extreme caution and care in collecting data before publication. Mymoneytimes does not liable for the adequacy, accuracy or completeness of any given information. Hence we are not liable for any kind of direct or indirect loss caused by the use of such information.