Projects running behind schedule decline to 25-month low in February

In February, delayed central government projects declined to a 25-month low of 41.2%, while the cost overrun ratio dropped to a three-month low of 18.19%. With 1,902 projects monitored, 443 faced cost overruns and 764 experienced time overruns, with average delays exceeding 36 months for many projects. Railways and roads sectors were notably affected.
Read The Rest at :