MoSPI says 449 infra projects hit by cost overrun of Rs 5.01 lakh cr in March

By Economic Times - 7 months ago
The total original cost of these projects was Rs 26,87,535.69 crore, but their anticipated completion cost is expected to be Rs 31,88,859.02 crore, representing an 18.65% increase. The report noted that out of 1,873 projects, 779 were delayed, with reasons including land acquisition delays, environmental clearances, and infrastructure support issues

Disclaimer : Mymoneytimes implements extreme caution and care in collecting data before publication. Mymoneytimes does not liable for the adequacy, accuracy or completeness of any given information. Hence we are not liable for any kind of direct or indirect loss caused by the use of such information.