Govt says 448 infra projects hit by cost overrun of Rs 5.55 lakh cr in Oct-Dec

By Economic Times - 7 months ago
The Quarterly Project Implementation Status Report (QPISR) for the third quarter of 2023-24 revealed that 448 infrastructure projects, each worth Rs 150 crore or more, experienced cost overruns of over Rs 5.55 lakh crore. Out of 1,897 projects, 56 were ahead of schedule, 632 were on schedule, and 902 were delayed. The anticipated completion cost was Rs 31,74,489.91 crore.

Disclaimer : Mymoneytimes implements extreme caution and care in collecting data before publication. Mymoneytimes does not liable for the adequacy, accuracy or completeness of any given information. Hence we are not liable for any kind of direct or indirect loss caused by the use of such information.