In February, delayed central government projects declined to a 25-month low of 41.2%, while the cost overrun ratio dropped to a three-month low of 18.19%. With 1,902 projects monitored, 443 faced cost overruns and 764 experienced time overruns, with average delays exceeding 36 months for many projects. Railways and roads sectors were notably affected.
Disclaimer : Mymoneytimes implements extreme caution and care in collecting data before publication. Mymoneytimes does not liable for the adequacy, accuracy or completeness of any given information. Hence we are not liable for any kind of direct or indirect loss caused by the use of such information.